V557 Initial plan: when it starts
Written V0557 on the CMS-2567 and in QCOR.
Cited on this tag? What happens after a citation · One-page sheet for the binder
The regulation
§ 494.90(b) Standard: Implementation of the patient plan of care. (2) Implementation of the initial plan of care must begin within the [later][sic] of 30 calendar days after admission to the dialysis facility or 13 outpatient hemodialysis sessions beginning with the first outpatient dialysis session…
Appendix H quotes this text a little differently from the regulation as published today. The eCFR has the current wording.
CMS's interpretive guidance
Interpretive Guidance § 494.90(b)(2)
The timeline for both the completion of the initial comprehensive assessment and the beginning of implementation of the initial patient plan of care is the later of 30 days from the date of admission or 13 hemodialysis treatments at the facility. Refer to V516. For patients who have more than 3 treatments a week, e.g., those on peritoneal dialysis or daily/nocturnal hemodialysis, the plan of care is expected to be completed within 30 days from the date of admission, excluding any days the patient is hospitalized during that period.
The plan of care should be dated to indicate when the plan was initiated. Although the plan of care must be initiated within the required timeline, the schedule for full implementation of the plan will vary depending upon the complexity of the plan.
In order for dialysis treatment to be initiated, each patient must have an initial dialysis prescription, orders for care, and baseline physical and nursing assessments before treatment is begun at the facility. See V715 under the Condition for medical director for this requirement.
Questions on this site that cite it
https://middlemolecule.com/rulebook/tags/v557/